G1509, Revised September 2003

Controlling Runoff and Erosion at Urban Construction Sites

Bob Broz, Don Pfost and Allen Thompson
Biological Engineering Department

Runoff from construction sites is the major source of sediment in urban areas under development. There are two main reasons why construction activities increase pollutant loads in runoff. First, the volume and rate of runoff typically increase, providing a larger capacity to transport pollutants to rivers and lakes. Second, the vegetation is removed, leaving bare soil that is much more vulnerable to erosion, resulting in sediment moving into receiving waters. Typical sediment loading rates from construction sites vary from 100 to 200 tons per acre per year and can range up to 1,100 tons per acre per year.

Note
For farmland to maintain its productive capacity, erosion should be limited to no more than 1 to 5 tons per acre per year, depending on soil type.

Raindrop impact is the major cause of soil particle detachment (Figure 1), which can result in the particles moving down slope in flowing water (as sheet erosion) during a rainfall event. Flowing water can also detach soil particles if the velocity is high enough, usually where water starts to concentrate (rill and gully erosion in Figure 1). If the velocity is reduced sufficiently, particles will settle out. The velocity at which settling begins is dependent on particle size and density, as is the time required for the particles to settle out. Large, dense particles, such as grains of sand, settle first. Fine clays settle out slowly and only in relatively still water.

Types of soil erosion Figure 1
Types of soil erosion.
 

Erosion control measures can disrupt the phases of erosion by providing soil stabilization, runoff management and sediment control (Figure 2). By preventing splash, sheet and rill erosion, soil stabilization measures (such as soil amendments, vegetation, and mulch) can interrupt the first phase of the erosion cycle, the detachment of soil particles. Vegetative cover can provide effective soil stabilization, but sometimes the vegetation needs the extra stability and protection of additional measures such as erosion control blankets, silt fences, terraces, and diversions.

This publication discusses typical practices to reduce erosion and retain sediment on construction sites. Erosion- and sediment-control structures should be installed and maintained in accordance with local jurisdictions, manufacturers' specifications or engineering drawings.

Construction Site Inspection Form PDF

Vegetative cover

Vegetative cover is normally the most effective and practical control of erosion and sediment loadings but takes time for establishment. Sodding can reduce the time required for grass establishment and can be used to control erosion in some channels in lieu of riprap or concrete. The roots of vegetation, such as grass, binds soil particles together to resist erosion. Vegetation helps absorb the impact of raindrops to prevent detachment of soil particles. Vegetation can flatten and, like shingles on a roof, allow the runoff to flow above the soil. Stiff, standing vegetation can slow runoff (which may allow larger particles to settle out) and act as a filter to remove soil particles from flowing water.

Consider leaving vegetated strips in phased construction projects to slow runoff and trap sediment. These strips may have grass cover or woody vegetation. Vegetated cover may act as a filter strip at intervals down a slope or as a filter/buffer along a stream or body of water. Table 1 provides guidelines for minimum strip widths of grass or forest for various slopes.

Erosion process Figure 2
A. Erosion process
B. Possible points of intervention
 

Table 1
Recommended filter strip widths for various slopes.

Temporary vegetative cover
Disturbed construction sites should be seeded as soon as possible to provide economical erosion control. Annual plants which sprout rapidly and survive for only one growing season may provide adequate cover for up to 12 months. Plant materials, lime and fertilizer requirements, and seeding rates and times should be specified by as qualified professional. (Table 2 has typical seeding rates if no plan is available.) Fertilizer and lime, if needed, should be incorporated 3 to 6 inches into the soil. Soil should be tilled 3 inches deep for drilling or broadcast seeding. No-till drilling may be possible if the soil is not excessively compacted. Large seeds such as small grains should not be planted over 1.5 inches deep; small grass and legume seeds should not be planted over 1/2 inch deep. Mulching is recommended to conserve moisture and reduce erosion.

Table 2
Plant materials and minimum rates for temporary seedings.

*If vegetative cover will be required for more than a year, consider adding fescue or another permanent species to the seeding mixture.

Permanent vegetative cover
A perennial vegetative cover should be considered for sites where protection will be needed for more than 12 months. This practice is used where vegetation is desired to permanently stabilize the soil, e.g., to protect channels, dikes and embankments. As with temporary seedings, care is required to establish a good, thick cover of permanent grass. Stockpiling topsoil to be redistributed at the finish grading will aid in establishing a permanent vegetative cover. Legumes may be added to the seeding mix to provide nitrogen and to provide growth during hot, dry weather when some grasses are dormant.

Seedbed preparation and other cultural practices are similar for temporary and permanent seedings. Nurse crops, such as wheat or rye, may be added to the seeding mix to reduce weeds, control erosion and provide winter protection for seedlings. Plant materials, lime and fertilizer requirements, and seeding rates and times should be specified by a qualified professional. (Table 3 shows typical seeding rates.) Mulching is recommended to conserve moisture and reduce erosion.

Table 3
Minimum seeding rates for permanent seedings.

*PLS is pure, live seed. Example: If the seed is 95 percent pure and has 90 percent germination, the PLS is 85.5 percent [0.95 x 0.90 = 0.855]. To calculate the amount of this seed to plant 80 pounds of PLS per acre would require 80/0.855 = 93.57 pounds per acre.

Vegatative cover Figure 3
Vegatative cover on a slope.
 

Mulch

Natural mulch
Natural mulch, such as straw and wood chips, and artificial mulch, such as geotextile (fabric) rollout blankets, are effective in absorbing raindrop impact to reduce soil detachment and are effective as soon as they are applied. Mulch is normally used in combination with seeding to provide ground cover during the establishment period for a temporary or permanent vegetative cover. Disadvantages of a strawlike mulch are that it can blow or wash away. Various binding agents (e.g., asphalt tackifiers) and netting are available to help hold straw in place (Figure 3). Netting and the blanket-type mulches described below can be pinned in place.

Temporary truck entrance Figure 4
Temporary truck entrance at construction site provides all-weather access and reduces tracking of mud onto roads.
 

Geotextile erosion control blankets
Some geotextile erosion control blankets are organic and biodegradable and can be used in combination with seeding to control erosion until a permanent vegetation is established. They can also be used to replace rock riprap or concrete in channels (green engineering). Other types of geotextile blankets are inorganic and nonbiodegradable. Some of these can be used in combination with seeding to control erosion until a permanent vegetation is established and to provide a permanent supplement to the seeding. Some types can be used as silt fences. Geotextile underlayment can be used on soft subgrades for both temporary graveled access to construction sites (Figure 4) and permanent gravel roads or as an underlayment for riprap and rock dams.

Soil amendments

Polymer soil amendments known as polyacrylamides (PAM) can help bind soil particles together to reduce erosion and sedimentation. When used on bare soil, without seed or mulch, anionic PAM should be used on slopes 3:1 or flatter. Polyacrylamides are not a cure-all, but they can be a good addition to other sound management practices. Both laboratory and field demonstrations of the effectiveness of PAM in Missouri show that they can significantly reduce loss of soil from agricultural and construction sites. Hydroseeding equipment used for seeding, fertilizing and mulching disturbed ground can be an effective way to deliver polyacrylamides. For more information about the use of PAM, contact Bob Broz or Allen Thompson at MU.

Silt fence barriers

A silt fence is a temporary barrier of geotextile fabric (filter cloth) used to intercept sediment-laden runoff from small drainage areas. A silt fence can be used to promote sheet flow, to reduce runoff velocity, and to help retain transported sediment on the site, thus reducing erosion and enhancing water quality. The expected life span of a silt fence depends on the type of fabric used and its ultraviolet stability. Silt fences are usually installed on the contour with each end turned upslope, causing the runoff to form a pond.

Typical specifications for silt fence filter fabric.

Types of silt fence barriers
There are two general types of silt fence barriers — filter barriers and silt fences

Where silt fences are used
Silt fences are commonly placed at intervals on a disturbed slope or adjacent to streams and ponds. Silt fences have a lower failure rate than straw bale barriers but are more expensive. Silt fences can be used for slope protection, in minor swales or ditches, and around storm drains.

Slope protection
The maximum size of the drainage area should be 0.25 acre per 100 feet of fence; the maximum length of slope behind the fence is 100 feet. Table 4 shows the maximum length for given slopes.

Table 4
Allowable slope length above silt fences or straw barriers.

A silt fence may be used around or downslope of soil stockpiles and along the sides of streams and ponds.

Channel/storm drain application

Installation of a silt fence barrier Figure 5
Installation of a silt fence barrier for sheet flow.
 

Basic design and construction criteria

TCross-section detail of installed silt fence Figure 6
Cross-section detail of installed silt fence.
 

Common trouble points

Straw bale barriers

A straw bale barrier is a temporary entrenched and anchored barrier used to intercept sediment-laden runoff and to provide some retention of sediment from small drainage areas. A straw bale barrier can be used to promote sheet flow and to reduce runoff velocity, thus reducing erosion and improving water quality. The expected life span is normally three months, therefore straw bales must be replaced or a new barrier placed directly upslope of the old when a barrier is required for longer time periods. An average straw bale should be 30 inches long, weigh at least 50 pounds, and contain at least 5 cubic feet of material.

Where straw bales are used
Straw bales can be used for slope protection in disturbed areas to control sheet and rill erosion or in minor swales or ditches to trap sediment-laden runoff. Straw bale barriers may also be used around or downslope of soil stockpiles.

Slope protection
Recommended maximum size of the drainage area is 0.25 acre per 100 feet of straw bale barrier fence length; the maximum length of slope behind the fence is 100 feet; and the maximum slope length for given slopes is as specified in Table 4. These limitations are similar to those for silt fences. See Figure 7a for typical installation.

Channel application

Installation of straw bale barrier Figure 7a
Installation of a straw bale barrier.
Cross-sectional view of an installed straw bale Figure 7b
Cross-sectional view of an installed straw bale.
Check dam and a sediment trap Figure 7c
Installation of a straw bale barrier in a channel to act as a check dam and a sediment trap.
 

Basic design and construction criteria
A trench 4 to 6 inches deep should be excavated to the length of the barrier and the width of the bale, as shown in Figure 7b. Excavated material should be placed on the upstream side of the trench. Wire or string-bound bales containing at least 5 cubic feet of either hay or straw are placed in the trench and should be anchored by two 2 x 2 wooden stakes or rebar steel pickets driven through the bale into the underlying soil at a slight upstream angle to help prevent the bale from overturning. The first stake should also be driven slightly toward the previously laid bale to force them together. Spacing between the bales should be tightly chinked with loose straw. The excavated soil can now be backfilled firmly against the upslope side and compacted.

For straw bale check dams in swales or ditches, place the barrier across the swale such that the ground level at the end of the bales is higher than the top of the lowest middle bale (Figure 7c). This will prevent scouring due to flow around the ends of the barrier.

Fiber rolls/logs
Fiber rolls (or logs) can substitute for straw bales or silt fences in some situations with a savings in labor to install. The rolls are typically 8 to 20 feet long and 8 to 20 inches in diameter. One vender includes five stakes with a 10-foot excelsior log, which can replace three straw or hay bales. The 10-foot log weighs 3 pounds per linear foot in a 12-inch diameter and 5 pounds per linear foot in an 18-inch diameter. Fiber rolls are more aesthetically pleasing, but the cost may be 7 to 8 times as much as a silt fence.

Temporary silt fence sediment trap Figure 8
Temporary silt fence sediment trap to control runoff.
 

Temporary sediment trap

A temporary sediment trap is a control device used to intercept sediment-laden runoff and to trap sediment and prevent or reduce off-site sedimentation. A temporary sediment trap can be formed by excavation or by embankments constructed at designated locations accessible for cleanout (Figure 8).

Where temporary sediment traps are used
A temporary sediment trap may be located in a drainageway, at a storm drain inlet, or at other points of discharge from a disturbed area. They may be constructed independently or in conjunction with diversions. They may be used in most drainage situations to prevent excessive siltation of pipe structures. Designs may vary from a low-cost straw bale or silt fence to a more elaborate gravel and riprap structure.

Gravel and riprap type sediment trap/basin Figure 9
Gravel and riprap type sediment trap/basin.
 

Basic design and construction criteria

Common trouble points

Maintenance
Inspect temporary sediment traps after each significant rainfall event and repair any erosion and piping holes immediately. Trap should be cleaned out when sediment reaches half the design depth; a stake set at the cleanout level is helpful. Gravel facing should be cleaned or replaced if clogged. Check spillway depth periodically to ensure at least 1.5 foot depth.

Removal
Do not remove the sediment trap until all sediment-producing areas have been permanently stabilized. The accumulated sediment in the trap should be removed, and all excavation should be backfilled and properly compacted. Smooth the site to blend with the terrain or as specified on plans.

Diversions

A diversion is a berm (dike or ridge) or a swale (excavated channel or ditch) used to prevent sediment-laden waters from leaving a site and to prevent off-site or upstream waters from entering a site. Typical diversions are a combination berm/swale and may be temporary or permanent structures.

Where diversions are used

Temporary diversions
This practice applies wherever stormwater runoff from areas less than 5 acres must be temporarily diverted to protect disturbed areas and slopes or to retain sediment on site during construction. These structures generally have an expected life of 18 months or less and should be vegetated if expected to be left in place more than 30 days. Diversions should be designed by a registered design professional to handle the peak runoff from a 10-year storm. The channel grade should be positive toward the outlet but flat enough to produce nonerosive velocities. Outlets should be stabilized to prevent erosion and convey runoff to a point where it will not cause damage. Temporary diversions may be removed and blended with the natural topography when the area protected is permanently stabilized.

Permanent diversions
Permanent diversions are used wherever stormwater from less than 5 acres can be redirected to protect downslope structures or areas from erosion, sediment and excessive wetness or localized flooding. They are designed to intercept and carry excess water to a stable outlet, where it can be temporarily stored or released. Vegetation should be established on ridges and channels as soon as possible or use synthetic erosion control measures as specified in the design. Maintain vegetation with periodic fertilization and mowing to keep plantings in a vigorous, healthy condition.

Check dams

Check dams are small, temporary dams constructed across a swale or channel. They can be constructed using gravel, straw bales, sand bags or fiber rolls. They are used to reduce the velocity of concentrated flow and, therefore, to reduce the erosion in a swale or channel. Check dams should be used when it is not feasible or practical to line the channel or implement permanent flow-control practices. Check dams are usually installed such that the crest of a dam is level with the toe of the next check dam (if any) upslope.

Rock dam sediment basins

A rock embankment may be used as an alternative to a standard sediment basin for a drainage area of 20 acres or less. It may be preferable to standard sediment basins where an earthen embankment would be difficult to construct. Dam height is normally limited to 8 feet and the design life to three years. Well-graded, hard, angular, durable stone with a d50 of 9 inches minimum is recommended. Rock dams can double as check dams and sediment basins.

Inlet protection

A temporary, woven, high-strength geotextile barrier can be placed around a drop inlet to prevent sediment from entering storm drains during construction. This practice applies where early use of the drains is necessary. The practice is limited to a drainage area of 1 acre per inlet, designed for a 10-year, 24-hour storm. Set stakes close to the drop inlet so that overflow falls into the structure and not on unprotected soil. Straw bales, fiber rolls, sand bags and gravel berms may be used in lieu of fabric. Straw bales should be set back 12 to 24 inches from the inlet.

Effectiveness of basic erosion control practices.

References

G1509, revised September 2003

G1509 Controlling Runoff and Erosion at Urban Construction Sites | University of Missouri Extension

Order publications online at http://extension.missouri.edu/explore/shop/ or call toll-free 800-292-0969.

University of Missouri Extension - print indicia